The process

From first call to first kilowatt — here's exactly what happens

We've done this enough times to make it smooth. Here's the full process, step by step, with no surprises.

01Free site assessment1–2 weeks
02Custom system design2–3 weeks
03Permitting and approvals4–8 weeks
04Installation3–7 days
05Inspection and activation1–2 weeks
01
1–2 weeks

Free site assessment

We start with a no-cost, no-obligation assessment of your gym. We review your utility bills, measure your roof, check for shading, and evaluate your electrical infrastructure. You'll get a clear picture of what a system would look like — and what it would save — before any money changes hands.

  • 12-month utility bill review
  • Roof measurement and structural check
  • Shading and orientation analysis
  • Preliminary savings estimate
Free site assessment
02
2–3 weeks

Custom system design

Our engineers design a system sized specifically for your gym's energy profile and roof. We model your production against your actual usage patterns — not generic averages — and present you with a detailed proposal including system size, equipment specs, projected output, incentives, and financing options.

  • Custom production modeling
  • Equipment selection and layout
  • Incentive and tax credit analysis
  • Financing options (cash, loan, lease, PPA)
Custom system design
03
4–8 weeks

Permitting and approvals

We handle all the paperwork — building permits, utility interconnection applications, HOA approvals if needed, and any structural engineering sign-offs. This is the part that trips up most solar projects. We've done it dozens of times and know how to keep it moving.

  • Building permit filing
  • Utility interconnection application
  • Structural engineering if required
  • Incentive program enrollment
Permitting and approvals
04
3–7 days

Installation

Our installation crews work efficiently to minimize disruption to your gym operations. Most commercial installs are completed in under a week. We handle all equipment delivery, racking, wiring, and inverter installation — and we leave the site cleaner than we found it.

  • Racking and panel installation
  • Inverter and electrical work
  • Minimal disruption to gym operations
  • Full site cleanup on completion
Installation
05
1–2 weeks

Inspection and activation

After installation, we schedule the utility inspection and coordinate permission to operate (PTO) from your utility company. Once approved, we flip the switch and your system goes live. We walk you through your monitoring portal and make sure you know exactly what you're looking at.

  • Utility inspection coordination
  • Permission to operate (PTO)
  • System commissioning and testing
  • Monitoring portal walkthrough
Inspection and activation
Solar monitoring dashboard

After install

Ongoing monitoring — we watch it so you don't have to

Every system we install includes remote monitoring. We track your production 24/7 and alert you if anything looks off. Most issues are resolved remotely before you even notice them. Your job is to run your gym — ours is to make sure the solar keeps working.

  • Real-time production data
  • Automated fault detection
  • Monthly performance reports
  • 25-year production warranty
3–5
months

Total timeline: 3–5 months from first call to first kilowatt

The permitting phase is the longest variable — it depends on your local jurisdiction and utility. We've seen it take 3 weeks and we've seen it take 10. We'll give you a realistic estimate for your area upfront.